MCB Installation on Transjakarta Lane Reaches 108 KM
access_time May 18 2016 02:03 PM remove_red_eye 1287
Reported by Suriaman Panjaitan | Translated by Rizky Mawardi
Reported by Suriaman Panjaitan | Translated by Rizky Mawardi
The installation of road separator or movable concrete barrier (MCB) at 12 Transjakarta corridors is accelerated. Up to today, the installation has reached 108 kilometers.
We have installed along 108 kilometers. Our target for this year is 120 kilometers
Jakarta Head Dept. of Bina Marga, Yusmada Faizal, said total lane length for 12 corridors is 420 kilometers. Of that total, his side only instals along 300 km, since the remaining 120 km is a crossroad and u-turn.
“We have installed along 108 kilometers. Our target for this year is 120 kilometers,” he said, Tuesday (5/17).
MCB Installed on Jalan Kramat RayaHe explained that the installation of MCB for 120 kilometers uses 2016 City Budget. The effort will be also continued next year by 180 kilometers.
“If possible, we will propose for additional budget. It aims to run all the project this year,” he added.